Hope & Clay Construction Ltd.

Queen Elizabeth Barracks


Church Crookham


Roadworks


www.hopeandclay.co.uk
Tweseldown Road

1.
Works Description

       The installation of raised tables, kerb realignment and improvement of existing drainage.
2.
Programme

       These works are to commence on 22nd July 2013 and last approximately 8 Weeks. There will be some initial works during week commencing 10th June 2013, to replace manhole covers and investigate the current drainage system.

  3.  Interfaces / Traffic Management

      

         The works will be carried out under a Road Closure, with access being provided. At times access will be restricted and some minor delays may be experienced.

A drawing of the works can be found by clicking here.

Our intended programme can be found by clicking here.